1400 West Randolph is on its way up in the far-off West Loop

1400 West Randolph

1400 West Randolph will deliver 278 apartments to the far reaches of the West Loop.

Marquette Companies has a pair of residential developments under construction at the outer reaches of the West Loop. This one, 1400 West Randolph, should make quite a statement when rises to its full 26-story height.

1400 West Randolph is situated on the corner of Randolph and Ogden. It 278 rental units (studio, one-, two-, and three-bedroom apartments) and 10,000 square feet of ground-floor retail space. Construction has been underway since last year, when foundation, tower crane and full-build permits were all issued.

Brininstool + Lynch is the design architect.

Below you’ll see progress photos from December 2020 and March 2021 visits. That’s Power Construction on the build. Marquette plans an early 2022 opening.

 

First Visit (in the nick of time): Optima Lakeview lowers the boom

Optima Lakeview March 2021

Optima Lakeview is topped out and moving toward a 2022 opening.

My first visit to Optima Lakeview last week was just in time.

The tower crane is coming down from the topped-out T.O.D. from Glencoe’s Optima. Consisting of 198 apartments and 14,000 square feet of ground-level retail space, with parking for 94 cars and 208 bikes, the seven-story development is expected to open next year.

Optima Lakeview is another role model for do-it-yourself’ers. Optima is handling development, design, and general contractor duties.

Here now, you have your basic construction photos, and then a few shots of tower crane dismantling from March 16.

 

Stubless, progress-less 1000M takes another beating

Its caissons are done, the tower crane stub was set, and things were rockin’ and rollin’ at 1000M, the new residential tower next to Grant Park in the South Loop. But it hasn’t seen new progress in almost a year now, and Crain’s Chicago Business reported Monday that no one within the potential shadow of the future tower seems at all pleased with the new direction developers would like to take the tower in. Apartments? Condos? A mix? Heck, even that website seems to be dead.

Bummer. Here are a couple shots of the sad, idle construction pit at 1000 South Michigan Ave.

First Visit: Gild gets underway in the Gold Coast neighborhood

Gild Chicago March 2021

Gild, at State and Division in Gold Coast, is underway.

A bunch of short stuff was demolished to make room for a not-as-short apartment building at 1210 North State.

Gild is coming to Gold Coast. This 12-story, 89-unit apartment building from Newcastle Limited will also include nearly 18,000 square feet of retail space. It is a design by CallisonRTKL, and is being built by Power Construction.

Progress Update: 300 North Michigan

300 North Michigan

300 North Michigan between the Magnificent and Cultural Miles of Chicago’s Michigan Avenue.

There aren’t many projects happening in Chicago that this blog considers “mixed-use.” Since everything includes retail these days, an office tower or residential building with ground-floor commercial space doesn’t split the vote.

300 North Michigan qualifies as mixed-use. The bKL Archtecture-designed tower will deliver 289 residential units and 280 hotel rooms across its 47 stories. A joint venture between Sterling Bay and Magellan Group, 300 North Michigan got its tower crane permit back in August 2020, and its foundation permit (with an assigned address of 88 E Wacker Pl) about three weeks prior. The full-build permit arrived in late September.

Linn-Mathes is the general contractor.

 

First Visit: Clarendale Six Corners erects a tower crane *Updated*

Clarendale Portage Park

Clarendale Six Corners gets a tower crane.

**This post was updated April 15, 2021 to reflect the correct name of this project, Clarendale Six Corners.**

Last week saw Chicago’s northernmost and westernmost tower crane erected at the Six Corners intersection of Irving Park, Milwaukee, and Cicero.

Clarendale Six Corners was issued a foundation permit back in January. That permit calls for a 10-story building with a total of 258 units. 114 of those units will be residential, 98 will be assisted living, and 46 will be memory care.

With a development assist from LCS,  Ryan Companies is your developer, design architect, and general contractor on this one. That’s peak keeping-it-in-house.

Shout-out to Adjustable Concrete Construction for the info and a rendering of The Clarendale.

And now, as is usually the case on this blog, please enjoy far more Tower Crane Erection photos than you’ll ever need, with a few foundation pics thrown in for good measure.

Cirrus Condos, Cascade Apartments nearing completion

Cascade Cirrus

Cirrus Condominiums and Cascade Apartments rise in Lakeshore East.

If you’re ever unsure which tower is Cascade and which is Cirrus, remember that Cirrus is taller, and it has the better views of Lake Michigan. You give the condos better views.

Quick refresher, then we’ll roll the photos.

300 North Michigan drills caissons, scores a tower crane

A tower crane permit was issued yesterday, August 27.

Design Architect: bKL Architecture

Developer: Sterling Bay

Developer: Magellan Development Group

GC:Linn-Mathes

An August walk-around at One Chicago

All photos taken back on August 17. The way it’s going up, One Chicago might be finished by now.

CG: Power Construction

Developer: JDL Development

Design Architect: Hartshorne Plunkard Architecture

Design Architect: Goettsch Partners 

One of these is Cascade; One of these is Cirrus; Two of these are cool

Photos from August 17

Design Architect: bKL Architecture

Developer: Magellan Development Group

GC: Lendlease