At The Sinclair, glass is almost up, and the tower crane is almost down

The Sinclair

Tower cranes aren’t supposed to be lower than the top of the buildings their servicing. Unless they’re being removed.

The tower crane started coming down from The Sinclair last week. That may seem like sad news, but the glass is also more than half full, which is good news. So they cancel each other out.

McHugh Construction has been working on the Fifield Companies apartment tower since Winter 2015. Now, after two tower cranes and lots of concrete, the 35-story, 390-unit tower looks certain to make its Summer Opening goal.

 

 

One Grant Park plants a tower crane

One Grant Park tower crane

Scratch One Grant Park off the tower crane waiting list.

https://twitter.com/PDNAChicago/status/847801738648268800

Thanks to that tweet from Twitter user @PDNAChicago, we now know One Grant Park has begun installing a tower crane. The crane permit was granted (heh…Granted) way back on February 1, so it’s been a long wait.

The highly-anticipated Rafael Viñoly Architects design for Crescent Heights is delivering 76 stories and 792 apartments, plus 12,000 square feet of retail space, to the South Loop intersection of Roosevelt Road and Michigan Avenue.

Soon, McHugh Construction will have a new tower crane with which to begin sending One Grant Park into the sky. Hopefully, it won’t be a two-month wait like we had for the seedling. (Spoiler alert: It won’t be.)

 

 

Quick Look: The Sinclair tower crane is coming down

The Sinclair tower crane removal

I wasn’t fast enough on the draw to capture the tower crane at The Sinclair coming down this morning as the Purple Line passed by. But I recovered in time to get this shot between the Sedgwick and Armitage stops. That rooftop crane will handle the rest of the heavy lifting from here on out.

McDonald’s goes three-dimensional. And I’m lovin’ it

McDonald's in 3D

The second floor is showing at the new McDonald’s Headquarters in the West Loop.

Life happens quickly. What did you expect from two tower cranes?

To no one’s surprise, the new McDonald’s Corporation Headquarters in the West Loop has lifted off the ground. After weeks of attending to ground-level matters (they’re still at it) McHugh Construction has started going vertical. That mostly good news, because now we can see what’s going on above the perimeter fencing, but bad news because no one with an adjacent balcony or rooftop has offered their vantage point to me for looking downward onto progress. Stuff is harder to see as it gets higher, you know.

Fact: Even in the snow, Vista Tower construction is still cool

Wanda Vista Tower snowy day

A cold, sunny day at Vista Tower.

While last week’s wintry weather threatened to slow down air traffic and snarl roadways, it didn’t cancel the show at Vista Theater, as McHugh Construction crews plowed through snowy conditions to continue progress at Vista Tower.

Similar to the McHugh project over at the new McDonald’s HQ, Vista Tower seems to have several separate sections of different activities ongoing, from holes being dug and ramps being started to the continuing extension of Upper Wacker Drive.

One request though, if I might add to the growing list of chores to be done: Can we get a pedestrian bridge over Field Boulevard? That long walk around The Tides, GEMS Academy, the Shoreham et al to get optimal views is starting to wear on me. Or maybe just have a tower crane hoist us across the Field void. Thanks.

One Grant Park is officially on tower-crane watch as caissons wrap up

One Grant Park

Case Foundation breaks down a caisson rig Thursday at One Grant Park in the South Loop.

Down at One Grant Park in the South Loop, Case Foundation has disassembled most of its caisson equipment and hauled it away. And while I’m no math genius, I couldn’t count more than one caisson on site that still awaits its concrete filling.

Now B.U.C. crews will be monitoring the lot at Roosevelt and Michigan 24/7, watching for tower crane parts to arrive. The City of Chicago issued that permit on February 1st, so somewhere there’s a free-standing Potain MD 485B seething to get into the game. It’s March Madness time; I say BRING IT ON.

It’s Craning Day at the Triple Hilton McCormick Place

Hilton McCormick Place tower crane

Thursday morning, this tower crane cab rolled past the B.U.C. HQ. On its way to the Hilton McCormick Place? Sure seemed like it.

Last week, we found the makings of a tower crane at the Triple-Branded Hilton Hotel at McCormick Place. That always means to be on high alert for assembly. Now, I can’t prove the crane parts I watched being driven down the Kennedy to the Dan Ryan this week were headed to McHugh Construction’s site, but it sure added up. A peek out the window Thursday morning confirmed that the crane was being set up down in the Prairie District. And field trip ensued, resulting in the following photos. Best guess is, assembly will be completed Friday.

Hilton McCormick Place tower crane

Way off in the distance, tower crane set-up has been spotted. Time to head to the South Loop.

Quick Look: Both tower cranes are up at McDonald’s

West Crane and East Crane are both assembled at Sterling Bay’s new McDonald’s Headquarters in the West Loop. East Crane gave us quite a ride, as it started up Saturday, only to have the tower top and cab removed Sunday. But Monday it was erected in full.

McDonald's Tower Crane duo

Monday evening’s view.

McDonald's Tower Crane duo

Tuesday morning’s view, with brief sunshine.

Yep, I got more from Wanda Vista Tower for ya

There’s still a lot going on, so why wouldn’t construction and skyscraper nerds take more photos? Really, it’s out of our control. So here ya go, another slew of action shots from this week at the ever-changing Vista Tower site.

Quick Look: Tower crane action in the West Loop and Prairie District

The McDonald’s headquarters is erecting the first of its two tower cranes, while the triple-branded Hilton Hotel at McCormick Place planted a tower crane seedling in the South Loop.