Progress update: The 808 Cleveland, topped out and soon-to-be sans tower crane

The 808 Cleveland has topped out.

DAC Developments’ The 808 Cleveland (808 North Cleveland Ave) topped out last month, putting another Chicago tower crane in danger of coming down in August.

The 22-story, 200-unit apartment tower by Pappageorge Haymes Partners is almost as glassy as it is tall, with just five levels of glazing remaining to be installed. That’s Focus‘s handiwork on the build.

The project team plans to have The 808 open for renters in Spring 2023, while also leasing about 28,000 square feet of retail and office space.

The following gallery was taken August 17, with a few photos from July 29 thrown in for good measure. Because I couldn’t bear to leave out a couple I took from Division Street and Halsted.

Enjoying the photos? Metra and CTA rides (and Amtrak trains to Milwaukee), Zipcars, Divvy Bikes, camera lenses, domain fees, snacks & energy drinks, and comfortable walking shoes add up. You can help offset expenses by making a greatly-appreciated donation to Building Up Chicago.

Checking back on The 808 Cleveland

First and foremost, a special thanks to the team of Focus and Pepper Construction for using their tower crane to pluck The Spirit of Progress from atop One River Place Condominiums and setting on top of The 808 Cleveland construction site so I could get the above photo op. The statue was returned to its proper place without anyone knowing she was missing.

And here are a bunch more photos I took of progress at Pappageorge Haymes Partners-designed, 22-story apartment building for DAC Developments that didn’t require me stealing a Chicago icon.

Enjoying the photos? Metra and CTA rides (and Amtrak trains to Milwaukee), Zipcars, Divvy Bikes, camera lenses, domain fees, snacks & energy drinks, and comfortable walking shoes add up. You can help offset expenses by making a greatly-appreciated donation to Building Up Chicago.

The 808 Cleveland exercises its verticality in the Near North

The 808 Cleveland at 808 N. Cleveland Ave in Near North

I bet you’ve noticed a couple tower cranes straddling Chicago Avenue and River North/Near North lately. Well, the one that isn’t yellow, the white one on north side of the street, is taking 808 North Cleveland vertical.

The 808 Cleveland is a 22-story, 200-unit apartment tower from DAC Developments. The Pappageorge Haymes Partners-designed tower will include a mix of studio units, one-bedroom, two-bedroom, and even four-bedroom co-living apartments. There’ll also be 28,000 square feet of office and retail space. The foundation permit, issued September 30 of last year, calls for 99 parking spaces. The tower crane was permitted October 29, and the full build permit arrived on December 6.

Focus is the general contractor; Pepper Construction is helping out on concrete.

Enjoying the photos? Metra and CTA rides (and Amtrak trains to Milwaukee), Zipcars, Divvy Bikes, camera lenses, domain fees, snacks & energy drinks, and comfortable walking shoes add up. You can help offset expenses by making a greatly-appreciated donation to Building Up Chicago.

167 Green Street drops its 2nd tower crane

The Banner waves as the West Tower Crane at 167 Green Street comes down.

With the removal of the second tower crane from 167 Green Street, Chicago now has no two-crane construction sites. There are a pair of three-crane jobs of course, at One Chicago Square and Cirrus/Cascade, but no pairs.

McDonald’s, Vista Tower, One Bennett Park, NEMA Chicago, Woodlawn Commons, and The Lincoln Common all recently utilized the double-tower-crane method to get stuff done. Now, 167 Green Street joins that list of completed missions.

Sunday, I took a quick walk around the West Loop site for one last look at the red Manitowoc MR608, affectionately known as West Crane, as crews worked on bringing it back to earth.

Construction Update: Soul City Church builds in the West Loop

Soul City Church

Soul City Church in the West Loop is building a three-story addition.

Soul City Church, at 1150 West Adams Street in the West Loop, filed a building permit with the City of Chicago back in October to complete a three-story addition next to the existing church. Now, Focus has erected the steel work for the 45,000-square-foot addition. When finished this summer, it will include a new auditorium, office space for church staff, and covered parking.

Soul City Church gets a permit to add on in the West Loop

Soul City Church

Soul City Church sits at the corner of Adams Street and Racine Avenue.

Soul City Church, at 1150 West Adams Street, is ready to undertake a major expansion of its facilities in the West Loop.

Wednesday, a permit was filed for Soul City to build a three-story addition in the empty lot next door to the east, as well as make renovations to the existing church. The construction will add a multi-level auditorium, church offices, lobbies, even a roof terrace for use by the Soul City congregation.

Neighbors of the West Loop was there when plans were presented back in June and has details of what’s to come now that the permit is filed, including Soul City’s plan to share use of its new addition with the neighboring community. Focus will serve as the general contractor.