They keep building Vista Tower, and we keep coming back to watch

Wanda Vista Tower

Looking east to west across the ever-changing scene of Vista Tower.They

Three weeks is far too long to go between photo galleries of what’s going on at Vista Tower. Especially when the landscape changes on a daily basis. McHugh Construction continues to entertain with lumber, rebar, concrete, and tower cranes. There’s a lot happening here, as you’re about to see.

Two cores compete for attention at Wanda Vista Tower

Wanda Vista tower two cores

It’s East Crane vs. West Crane in the Battle of the Cores at Vista Tower.

It’s time for another installment of Vista Tower Photo Gallery. What’s new in the New East Side? There are two cores competing for sunshine, the way trees do in a crowded forest. It would make a good reality show, if it wasn’t McHugh Construction responsible for building both segments. There’s no reason they crews at each core should compete against each other. Unless a passing photographer started some trash talk about how much faster West seems than East. But no one would do that. Right?

 

 

 

Fact: Even in the snow, Vista Tower construction is still cool

Wanda Vista Tower snowy day

A cold, sunny day at Vista Tower.

While last week’s wintry weather threatened to slow down air traffic and snarl roadways, it didn’t cancel the show at Vista Theater, as McHugh Construction crews plowed through snowy conditions to continue progress at Vista Tower.

Similar to the McHugh project over at the new McDonald’s HQ, Vista Tower seems to have several separate sections of different activities ongoing, from holes being dug and ramps being started to the continuing extension of Upper Wacker Drive.

One request though, if I might add to the growing list of chores to be done: Can we get a pedestrian bridge over Field Boulevard? That long walk around The Tides, GEMS Academy, the Shoreham et al to get optimal views is starting to wear on me. Or maybe just have a tower crane hoist us across the Field void. Thanks.

Yep, I got more from Wanda Vista Tower for ya

There’s still a lot going on, so why wouldn’t construction and skyscraper nerds take more photos? Really, it’s out of our control. So here ya go, another slew of action shots from this week at the ever-changing Vista Tower site.

Wanda Vista Tower starts going 3-dimensional

Wanda Vista Tower

Those kinds of heights are right about at my level. And you want me on that wall. You *need* me on that wall. 

Tired of Wanda Vista Tower photos yet? Don’t be. Because before you know it, all the fun construction will be hundreds of feet in the air, and much harder to watch. So let’s enjoy Vista Theater being presented by McHugh Construction while it lasts.

With the gigantic mat pour done (the junior mat at the east end of the site has been poured too), the tower has started going vertical. I was especially happy to see guys hanging on a wall, four feet off the ground. I could do that; anything over six feet high would have to be someone else’s job, though.

 

Why won’t the Wanda Vista tower cranes joust? Because they’re luffers, not fighters

Wanda Vista Tower two cranes

The two tower cranes of Wanda Vista Tower.

Wow. You clicked on this story, even after reading that headline? I owe you a drink or something.

Wanda Vista Tower has its two tower cranes up and running. Both are luffing cranes, with jibs that angle toward the sky, rather than staying parallel to the ground at all times.

Down at ground level, there’s enough rebar being installed in the foundation mat. If you feel the earth tilt a little extra in the coming days, it’ll be from all the concrete being poured into that thing.

Vista Tower Crane Update: East Crane is planted as West Crane blooms

Wanda Vista cranes

Even when they’re on the ground, tower cranes are cool.

West Crane will always be able to sneer at East Crane with a knowing, I-Was-Born-First smirk. But only by a couple of days. No sooner had construction crews rooted the first crane into the ground, the second one found a rebar bed of its own.

As one does when it’s about 10 degrees outside, dedicated skyscraper nerds (skyscraperds?) hung around Thursday afternoon to watch West Tower reach sky-cab status. Meanwhile, Eastie’s resting comfortably in place, waiting for concrete to be poured into its foundation.

There’s also the matter of the large hole in the middle of the site, that everyone but me seemed to be allowed to climb into. Unfair.

 

 

First of two Vista Tower cranes is in the ground

Vista Tower cranes

The two cranes of Vista Tower. West Crane, on the right, is set in its foundation. East Crane, to the left, is awaiting its turn.

Not only does Vista Tower win the First Tower Crane of 2017 Award, it wins the second tower crane of the year plaque as well.

Just as the City of Chicago promised us with the two permits filed on the last day of October and the second day of November, Vista Tower is putting two tower cranes into the freshly-caissoned ground in the New East Side neighborhood.

You’ll notice a striking difference between the two stub sections of crane that are now on site. “West Crane” where the taller towers of Vista will stand, looks like it’s on steroids when compared to “East Crane.” I wouldn’t advise messing with either of them, though.

Shout-out to bKL Architecture for being on-scene Tuesday morning and breaking the big crane news with an Instagram photo.

 

Vista Tower caisson work, second only to the Cubs as a spectator sport

Vista Tower caissons

Even the pigeons are mesmerized by caisson work going on at Vista Tower.

Vista Tower doesn’t need pre-sales of condo units. Just charge $5 for each one of us leaning against the railings along Wacker Drive, and by The Tides and The Shoreham atop Field Boulevard. It would raise a fortune.

Case Foundation continues to bore holes into the Lakeshore East earth, then fills them up with cement and rebar and corrugated metal tubes and even the occasional iron tube. Seriously, stop by and watch some time. Unless you have a meeting to go to. because you won’t make it back to the office in time.