GEMS World Academy Upper School gets permission to complete its latest assignment

With a permit issued Wednesday, the GEMS World Academy Upper School has official permission to complete its 13-story building in Lakeshore East. That allows Power Construction to continue their progress on the bKL Architecture-designed facility. Students are expected to start using the Upper School in Winter 2019.

You can watch progress for yourself by following this link to the youtube construction cam; the cam is also accessible from bKL Archtecture’s GEMS World Academy Upper School page linked above.

GEMS Academy Upper School wedging its way into small Lakeshore East recess

I desperately wanted to make some sort of school pun. Not sure the recess thing even makes sense, but I tried. Wedged as the new school is between Vista Tower construction and Coast apartment tower, it seemed like a decent analogy.

The Upper School at GEMS World Academy Chicago is rising at 355 East Wacker Drive. Designed by bKL Architecture, as was the first GEMS school, Power Construction has the task of completing the facility.

It’s caisson time for GEMS World Academy Upper School

GEMS Upper School caissons

Checking out a caisson from above at GEMS World Academy Upper School.

The Upper School at GEMS World Academy Chicago has begun caisson work at 355 East Wacker Drive. Case Foundation is on site digging long, slender holes in the ground and then filling them right back in with rebar and concrete.

Originally issued a foundation permit way back in March of 2015, the GEMS Upper School got a new caisson permit on September 20. Designed by bKL Architecture, as was the first GEMS school, Power Construction will take build the school atop the Case’s caissons.