I haven’t posted an update at 1400 South Wabash since May? That’s barely tolerable, if not entirely unacceptable. Let’s fix that now, as there’s been a lot of progress by Lendlease and Pepper Construction here. Looks like they’ve reached level 14-ish.
Some reminders:
Developer – CMK Companies
Design Architect – Pappageorge Haymes Partners
General Contractor – Lendlease
Concrete Contractor – Pepper Construction
30 stories
299 apartments
155 parking spaces
3,300 square feet of ground-level retail space
Scheduled opening – early 2023
Quirky-but-true fact – Green and Orange line trains practically run right through the parking deck