Pepper Construction began site prep last week at the new Columbia College Student Center in the South Loop.
A permit issued Friday sets the stage for work to begin on the Columbia College Student Center at Wabash Avenue and 8th Street in the South Loop. That would explain why a crew from Pepper Construction was on site last week, installing sidewalk protection and getting the lot prepped for activity.
Monday, Case Foundation posted on its Facebook page that they would begin drilling 57 rock caissons in March. With a little cooperative weather, Columbia plans to open the Gensler-designed student center late this year.
Despite the relatively wide footprint, at five stories, it’s not likely the new facility will require use of a tower crane, but we’ve reached out to Pepper to find out for sure. We should know soon.