808 West Van Buren foundation work continues

808 West Van Buren

Deep down, they’re still getting foundation work done at 808 West Van Buren in Greektown.

808 West Van Buren, the bKL Architecture-designed 12-story apartment building from Loukas Development, keeps setting its feet into Greektown, as Lendlease construction crews continue ground work in advance of the tower crane that will send the 148-unit apartment building vertical.

There’s a concrete pad against the north end of the lot, up against the existing building (314 South Halsted, the former home of The Parthenon, and a building getting some extensive work done in its own right) that looked like it could be a tower-crane pad, but what they’re erecting atop that slab doesn’t look much like a tower crane stub. We’ll keep our eyes out.

808 West Van Buren

10 days ago, looking at what I thought would be the tower-crane pad.

808 West Van Buren

See? That doesn’t look like tower crane space.